82. Deputy Naoise Ó Cearúil asked the Minister for Climate, Energy and the Environment the position regarding the acceleration of offshore wind development under the Climate Action Plan 2025, including progress on grid integration and planning reform; and if he will make a statement on the matter. [60514/25]
Sentiment score: 0.20
The climate action plan sets out ambitious offshore targets of 5 GW by 2030 and up to 20 GW by 2040. However, none of the offshore projects are yet operational as the Minister has mentioned and the first grid connections are not expected until 2028. Will the Minister outline how the Government intends to accelerate delivery, specifically the current offshore pipeline aligned with the climate action plan 2025 targets? What progress has been made on grid integration and planning reform to ensure those targets are actually met?
Sentiment score: 0.28
Gabhaim buíochas leis an Aire. We all share the same ambition but I fear there is now a growing gap sometimes between the aspiration and delivery. It is not just in relation to energy. We have been discussing this ad nauseam in terms of different areas of society. Seven phase 1 projects have maritime area consents, as the Minister mentioned, totalling around 4.2 GW, yet none are near construction. The delays in both grid readiness and planning are stalling process. I appreciate the Minister's involvement in trying to get things moving, particularly from a planning perspective and I appreciate how difficult it is. However, EirGrid's offshore grid connection policy is not due until 2026. It will be early next year, so not too far away. Developers still do not have clarity on connection costs or timelines. The maritime area planning regime, while welcome, has no statutory decision timelines. Anything around here needs timelines. An Coimisiún Pleanála lacks the resources and the expertise to process these applications quickly.
Sentiment score: 0.04
I thank the Minister. We need to look at introducing statutory timelines for consenting decisions and publish a delivery roadmap linking planning, grid and construction milestones. Without the joined up approach, we risk not only missing our 2030 targets but also the legally binding carbon budgets too, which is important to mention. It is not just about missing or meeting our climate targets. Offshore wind is Ireland's single biggest opportunity to secure our own clean energy, cut bills for families, as the Minister mentioned earlier, and build a new industry with long-term jobs along our coast. We have seen the success of onshore and of solar throughout the country and the expertise we have garnered in those two key areas. However, to realise the ambition, we need urgency and we need accountability from the various bodies in how projects can move from plans into generating power.
Sentiment score: 0.33